How Long Screed Takes to Dry Before Floor Finishes

Screed drying is quoted at about 1 mm a day, but the cut-off thickness differs by source and only a moisture test shows when a floor is ready.

Screed manufacturers quote BS 8204 for a rule of thumb of about 1 mm a day. Gyvlon puts the cut-off at 40 mm and Ronacrete puts it at 50 mm, so check the standard and the product data for your screed.

Rule of thumb, and where sources disagree

  • Calcium sulphate screed (Gyvlon): approximately 1 mm a day up to 40 mm, then 0.5 mm a day beyond, in very good conditions of 20 degrees C and 65% RH.
  • Sand and cement screed (Ronacrete): one day per mm for the first 50 mm, with more time per mm above that. It puts a 75 mm screed at around 100 days to reach 75% RH in good conditions.

Ronacrete adds that poor conditions of high humidity, low temperature and little ventilation take considerably longer. Gyvlon says the building should stay watertight and between 3 and 30 degrees C for the first 48 hours, with foot traffic possible after 24 to 48 hours.

Conditions move the number. Gyvlon says low temperatures and cold humid air above 70% RH greatly increase the days to dry, and good ventilation after 48 hours decreases them. It also says site conditions matter more than whether the surface is sanded.

For calcium sulphate screed, Gyvlon says:

  • Dehumidifiers can be used from 72 hours.
  • Underfloor heating can start commissioning from 7 days.
  • Non-load bearing partitions can be erected after 7 days.
  • Plasterboard and site materials can be loaded out after 7 days, but covering the screed for long periods can delay drying.
  • Do not hose the screed down to clean it.

Gyvlon adds that cementitious screeds can be sensitive to early moisture loss, so assisted drying differs by screed type.

It also says standard calcium sulphate screeds should ideally be sanded 3 to 10 days after installation. Mechanical preparation just before the final floor covering is applied removes surface contamination such as plaster, mortar and paint.

Fast-drying screeds exist. Ronacrete claims its FastDry Prompt screed reaches 75% RH at 50 mm after 4 days. That is a vendor claim from tests at 20 degrees C and 60 to 65% air humidity, and it has not been independently verified.

Proving it is dry

Ronacrete says most flooring products need a screed surface RH below 75%, and that bonded wood flooring needs a considerably lower moisture content.

Gyvlon, citing BS 8204 Part 7, says relative humidity testers are not accurate for calcium sulphate screed above 85% RH. It recommends a carbide method test (BS EN 13892-10) or oven drying at 40 degrees C to give a moisture content (%MC). Electronic resistance meters are a rough guide only.

Gyvlon gives this rough conversion:

  • 90% RH is about 1.5% MC.
  • 85% RH is about 1.0% MC.
  • 80% RH is about 0.7% MC.
  • 75% RH is about 0.5% MC.

Its table of maximum moisture for its standard screed runs from 0.4% for bonded engineered wood to 1.0% for unbonded carpet. The finish manufacturer's own limit governs the decision.

On the Gyvlon rule, a 75 mm screed takes 40 days for the first 40 mm and 70 days for the remaining 35 mm, a total of 110 days. Ronacrete's figure for the same thickness is around 100 days.

Common questions

Does underfloor heating speed drying?

Gyvlon says it can be commissioned from 7 days and greatly decreases the days to dry. It must be commissioned and recorded before a floor covering goes on.

Does sanding the surface shorten drying?

Gyvlon says the most critical factor is the site environment and not whether the surface is sanded.

Is a moisture meter reading enough?

Gyvlon describes electronic resistance meters as a rough guide only, varying widely in accuracy.

Can gas heaters be used to dry a screed?

Gyvlon says fossil fuel fired heaters, for example gas heaters, must not be used because they raise the humidity in the building.