Gateway 2, Gateway 3 and the Golden Thread Explained

GOV.UK guidance lists the documents behind Gateway 2 and Gateway 3, and the golden thread is the digital record that ties them together.

GOV.UK guidance on building control approval for higher-risk buildings says the client must get approval from the Building Safety Regulator (BSR) before starting a new higher-risk building. BSR data for the 12 weeks to 5 October 2026 shows a median of 23 weeks to approve new higher-risk buildings and conversions.

This page is general guidance, not legal advice. A higher-risk building has at least 7 storeys or is at least 18 metres high, and has at least 2 residential units or is a hospital or care home.

Gateway 2: approval before work starts

GOV.UK guidance calls this "building control approval". The industry calls it Gateway 2.

BSR first validates the application, then assesses it. The guidance gives 12 weeks for new higher-risk buildings unless an extension is agreed, and the outcome is approved, approved with requirements, or rejected.

Once approved, the submitted documents become "agreed documents". Changes are managed under the change control plan and recorded in the change control log. Work on a part of the project must stop until BSR approves any major change to that part.

The application must include an estimated commencement date. The client must tell BSR about any change of client, principal designer or principal contractor, and about notifiable or major changes.

BSR's median for complex new-build cases in the same data was 34 weeks nationally.

Gateway 3: the completion certificate

BSR issues a completion certificate if it is satisfied the work meets all relevant building regulations. A higher-risk building with at least 2 residential units cannot be registered without one.

If a partial completion strategy was submitted with the original application, it must be followed when applying for partial certificates. Where the building safety levy is payable, BSR cannot issue the certificate until the collecting authority confirms a valid notice of no charge or the levy is paid in full.

Documents the application lists

  • Drawings and plans
  • Construction control plan and change control plan
  • Mandatory occurrence reporting plan
  • Building regulations compliance statement
  • Fire and emergency file
  • Change control log
  • Compliance declarations signed by each principal designer and principal contractor
  • A client confirmation statement
  • A signed statement that building information has been handed over to the responsible person or principal accountable person

The golden thread

GOV.UK describes the golden thread as the information about a building. It must be kept digitally, secure from unauthorised access, available when needed, and treated as the building's single source of truth.

Handover

At completion the client hands the information to the principal accountable person or accountable person. That person must confirm they have received it and that it is in a format they can use.

What a finishing subcontractor is asked for

The guidance pages do not list subcontractor deliverables. The request comes through the main contract and the principal contractor's information requirements. Useful questions to put to the principal contractor:

  • Which drawing revision is the agreed document for this project?
  • How is a change to the work raised under the change control plan?
  • Which records from this project go into the fire and emergency file or the compliance statement?
  • What format and upload route does the golden thread use, and by when?

Approval times move with each BSR publication, so check the latest data before programming around any figure in this guide.

Common questions

Who must keep the golden thread on a new build?

GOV.UK says clients, principal designers and principal contractors on projects involving a higher-risk building. The client must provide a digital record-keeping system.

Can work start on part of a building before full approval?

Only on the approved parts. For a staged application, work on a stage cannot start until that stage is approved.

Does a validated application mean approval?

No. GOV.UK states that validation only confirms the required information is present.