Building Safety Act: What Subcontractors Must Know
Regulations 11A onwards of the Building Regulations 2010 put competence and information duties on every contractor, including specialists delivering one trade.
The Building Regulations etc. (Amendment) (England) Regulations 2023 (SI 2023/911) inserted a new Part 2A, starting at regulation 11A, into the Building Regulations 2010. It sets legal duties for clients, designers and contractors, and the contractor duties are written for any building work, not only higher-risk buildings.
This page is general guidance for specialist subcontractors and is not legal advice. Take advice on how the regulations apply to a specific contract. Check legislation.gov.uk for later amendments.
Who the duties cover
Where more than one contractor is working, or is reasonably foreseeable, regulation 11D requires the client to appoint a principal designer and a principal contractor in writing. That happens before the building control application for higher-risk work, or before the construction phase on other projects.
A specialist delivering one trade sits under the contractor duties. Regulation 11L(4) expressly covers a contractor "carrying out only part of the building work".
The client has duties too. Under 11A(4) the client must provide building information as soon as practicable to every designer and contractor on the project. Under 11L(1) a contractor must not start building work unless satisfied that the client is aware of the duties the client owes.
The competence test
Regulation 11F(1) says anyone carrying out building work needs the skills, knowledge, experience and behaviours to do it in line with all relevant requirements. For a firm, the test is organisational capability.
The test applies to both sides of an appointment:
- Whoever proposes to use a contractor must take all reasonable steps to satisfy themselves of competence before permitting the work (11E(2)).
- A contractor must not accept the work if it does not meet the test at the time of appointment (11E(6)).
Duties that sit with the subcontractor
Several contractor duties apply directly to site work:
- Plan, manage and monitor the work so it complies, and cooperate with the client, designers and other contractors (11J).
- Supervise and instruct workers under your control, with the information they need (11L(2)).
- Provide information about the work to help others comply (11L(3)).
- Report concerns about related work to the principal contractor (11L(4)).
- Advise whether work is higher-risk building work, if asked (11L(5)).
What changes in the supply chain
The principal contractor must coordinate the work of all contractors and take all reasonable steps to ensure they comply (11N). That gives a main contractor a legal reason to ask subcontractors for evidence of competence and records of the work.
For higher-risk building work, regulation 11E(2)(b) adds a specific question. The person appointing a contractor must ask whether a "serious sanction" has occurred in relation to them in the five years ending on the date of the appointment.
When their appointment ends, the principal designer and principal contractor must each give the client a document explaining the arrangements they put in place, no later than 28 days afterwards (11M(5), 11N(5)).
Questions to settle before accepting a project
- How does the firm evidence competence for this work, and who reviews it?
- What information about the work does the principal contractor expect, and when?
- Who raises a concern about adjoining work, and where is it recorded?
- Is any of the work higher-risk building work, and who decides?
If the principal contractor asked tomorrow how a firm shows its competence for a project, what would be on the table?
Common questions
What counts as a serious sanction?
Regulation 11E(8) defines it. It includes a compliance notice that referred to a contravention of Part A (structure) or Part B (fire safety) of Schedule 1, and a stop notice.
Can a trainee work on a project?
Regulation 11F(3) exempts an individual in training from the competence test. The person who asked them to work must make sure they are adequately supervised (11F(4)).
Where is the legal text?
Part 2 of SI 2023/911 on legislation.gov.uk contains regulations 11A onwards, inserted into the Building Regulations 2010.
Is this page legal advice?
No. It summarises regulation wording as general guidance, and a solicitor should advise on a specific contract or dispute.
Sources
- The Building Regulations etc. (Amendment) (England) Regulations 2023, Part 2 (legislation.gov.uk)
- The Building Regulations etc. (Amendment) (England) Regulations 2023, contents (legislation.gov.uk)
General guidance only. Check the current regulations and your project requirements.